ERCOT Interconnection Queue: Texas Energy Projects

Updated May 2026 • 8 min read

Figures on this page are from Load Factor’s queue data as of March 2026. Live totals, withdrawn requests included, are on the coverage page.

ERCOT's interconnection queue is smaller than PJM's and MISO's by project count, but it is one of the most traceable markets for developer research. Load Factor tracks 3,089 ERCOT projects, with a developer identified on 2,612 of them and only 477 unknowns.

That stands in sharp contrast to PJM, where 4,229 of 10,875 projects are still unknown, and reflects both the structure of ERCOT's market and the depth of Texas public records.

ERCOT Interconnection Queue by the Numbers

MetricERCOT
Total projects3,089
Projects with developer identified2,612
Unknown / unresolved477
State coverageTexas only
Map precision label on every projectYes

ERCOT's single-state footprint is both a constraint and a strength. Texas is one market, which means every project sits under the same state records, the same family of county records and the same ERCOT regulatory structure. That geographic concentration allows Load Factor to build evidence coverage more efficiently than in a multi-state ISO.

ERCOT Queue by Fuel Type

Fuel TypeProjectsCapacity (MW)
Battery Storage1,540246,279.3
Solar~800Substantial
WindSignificantLarge
HybridActiveActive

Battery storage is ERCOT's dominant queue story. With 1,540 standalone storage projects totaling 246,279.3 MW, ERCOT is second only to the Western markets in standalone storage application volume. Texas's merchant energy market, high renewable penetration, and frequent congestion events create sustained BESS economics that other US markets are only beginning to replicate.

Solar remains a central ERCOT story - Texas is the second-largest state for queued solar capacity nationally. Wind, which defined ERCOT's early renewable buildout, continues to hold a substantial position even as solar and storage have grown dramatically.

ERCOT's Geographic Complexity: No Published Coordinates

Unlike ISO queues that publish project-level coordinates, ERCOT does not publish latitude/longitude data in its GIS Report. The public data includes only county and point-of-interconnection (POI) substation name.

Load Factor places each ERCOT project as precisely as the public record allows, and labels every pin with how exact it is:

Pin precisionWhat it meansProjects
Project siteThe project's own location230
Plant siteThe location of the matching operating plant298
SubstationThe point of interconnection substation983
Line segmentThe midpoint of the line the project taps18
ApproximateThe county centre, where nothing better exists1,560

Load Factor displays coordinate confidence on every ERCOT project so users know whether a map pin is exact (substation-level) or approximate (county centroid). The 1,560 projects on county centroids are flagged - their pins are at the county center, not the actual project site.

Top ERCOT Markets: Where Development Is Concentrating

ERCOT's project geography follows the grid. Most ERCOT projects cluster near major transmission hubs in West Texas, South Texas, and the Panhandle - regions where wind and solar resources are strongest and where ERCOT's transmission build-out has historically directed development.

West Texas - the Permian Basin and adjacent transmission zones - holds the largest share of ERCOT solar and storage applications by MW.

South Texas sees heavy activity in the coastal and inland transmission zones, particularly for solar and hybrid storage. The Rio Grande Valley's solar resource and expanding transmission have attracted applications from large utility-scale developers.

The Panhandle and North Texas zones remain wind-dominant but are seeing increasing solar and storage overlap as battery costs have declined.

ERCOT Developer Intelligence: Why the Numbers Are Stronger Here

ERCOT's developer coverage reflects several structural advantages for Load Factor's evidence pipeline:

One state, one set of records. Every ERCOT project sits in Texas, so one set of state business records, one family of county public records and one regulator cover the whole market. In a multi-state ISO, each of those multiplies.

Operating-plant density. Texas has among the highest density of operating wind and solar plants in the US. A project that reaches operation shows up in federal plant records too, a second, independent record of the company behind it.

The same rules as everywhere else. A developer shows Two sources agree only when two or more independent primary sources name it. Where ERCOT attributions go further, it is because the records line up more often, not because the bar is lower.

ERCOT vs. PJM: The Developer Intelligence Contrast

The contrast between ERCOT (477 unknowns out of 3,089 projects) and PJM (4,229 unknowns out of 10,875 projects) is the starkest illustration of why single-ISO queue data does not translate across markets.

MarketProjectsDeveloper identifiedUnknown
ERCOT3,0892,612477
PJM10,8756,6464,229
MISO5,5453,9381,607

ERCOT's evidence advantage is real. If you are doing due diligence on a Texas project, Load Factor's developer identification is likely to give you a citable answer. If you are doing the same analysis on a Pennsylvania project, you are more likely to encounter an unresolved SPV - not because the developer cannot be identified, but because Load Factor's evidence coverage in Pennsylvania is still being built.

Frequently Asked Questions

How many projects are in ERCOT's interconnection queue?

As of March 2026, Load Factor tracked 3,089 ERCOT queue projects. That was smaller than PJM (10,875) and MISO (5,545), but one state's public records cover the whole queue, which makes it one of the most traceable markets for developer research.

Does ERCOT publish project coordinates?

No. ERCOT's GIS Report includes county and POI substation name but not latitude/longitude. Load Factor places each project as precisely as the public record allows and labels every pin with how exact it is. As of March 2026, approximately 1,560 projects fell back to county centroid approximations, which are flagged in the interface.

Which fuel type dominates ERCOT's interconnection queue?

As of March 2026, battery storage led ERCOT with 1,540 projects and 246,279.3 MW - the largest standalone storage queue of any named ISO. Solar and wind both remain substantial.

How do I browse ERCOT projects on Load Factor?

Filter by ERCOT on the Browse page. You can filter by fuel type, county, developer, and coordinate confidence. No account required.

Why is developer research easier in ERCOT than in PJM?

ERCOT's single-state structure means one set of state records, one family of county records and one regulator cover the whole market, and Texas's dense fleet of operating plants adds independent corroboration. PJM spans 13 states with more fragmented public records.

Browse all ERCOT projects | Battery storage in US queues | How developer attribution works | US Queue by the Numbers

See also: MISO Interconnection Queue | PJM Interconnection Queue | Battery Storage Queue Database

Browse the ERCOT Queue with Developer Intelligence

Load Factor tracks 3,089 ERCOT projects and who is developing them, with the evidence behind every name. Filter by fuel type, county, coordinate confidence, and developer. No account required for the public layer.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues

Book a 30-min walkthrough