Figures on this page are from Load Factor’s queue data as of March 2026. Live totals, withdrawn requests included, are on the coverage page.
MISO is the second-largest interconnection queue in the US by project count and one of the most analytically rich markets for developer-level research. Load Factor tracks 5,545 MISO queue projects across 13 states, with developer attribution on 3,938 of them.
No other major ISO in the country has comparable developer identification coverage. That makes MISO the clearest proof case for what forensic queue intelligence can look like when evidence depth is sufficient.
MISO Interconnection Queue by the Numbers
| Metric | MISO |
|---|---|
| Total projects | 5,545 |
| Projects with developer identified | 3,938 |
| Unknown / unresolved | 1,607 |
| Evidence records | Largest evidence share of any ISO |
Not every attribution has reached Two sources agree, and that understates the useful information available. Many MISO projects have developer identification at the inferred level: single-source attributions that are actionable for most research purposes even before a second independent source confirms them.
MISO Queue by Fuel Type
Solar leads MISO by project count, but the fuel mix is diverse enough to matter across all technology categories.
| Fuel Type | Projects | Capacity (MW) |
|---|---|---|
| Solar | 1,912 | 304,523.7 |
| Wind | 1,523 | 259,812.4 |
| Battery Storage | 839 | 122,434.5 |
| Hybrid | Various | 68,223.3 |
Solar's 304,523.7 MW makes MISO one of the largest solar pipeline markets in the country. The wind presence is also substantial - MISO's footprint across the Great Plains and Midwest positions it as a central wind market. Battery storage has accelerated in MISO, with 839 standalone storage applications adding 122,434.5 MW to the queue.
MISO Solar Queue by State: Arkansas Leads, Not Minnesota
MISO's geographic footprint spans 13 states from Louisiana and Arkansas in the South through Minnesota and the Dakotas in the North. The project distribution is more southern than most coverage of MISO implies.
| State | Solar Projects | Solar MW |
|---|---|---|
| Arkansas | 279 | 52,739.5 |
| Louisiana | 260 | 39,726.7 |
| Indiana | 226 | 36,237.7 |
| Illinois | 222 | 36,419.4 |
| Michigan | 260 | 36,044.2 |
| Minnesota | 151 | 22,211.7 |
| Mississippi | 128 | 20,086.6 |
| Wisconsin | 123 | 18,250.2 |
| Missouri | 71 | 12,702.2 |
| Iowa | 65 | 9,370.6 |
Arkansas leads by solar MW - not Minnesota, not Illinois, not the Corn Belt states that typically anchor generic MISO commentary. Arkansas (52,739.5 MW) and Louisiana (39,726.7 MW) together account for a larger share of MISO's solar pipeline than Indiana, Illinois, and Michigan combined.
At the county level, the concentration is even more specific. Jackson County, AR has 4,745.0 MW of queued solar. Mississippi County, AR has 3,600.0 MW. Calhoun County, AR has 3,094.5 MW. Henderson County, KY has 3,089.0 MW. Morehouse Parish, LA has 2,855.0 MW.
Top MISO Solar Developers: Evidence-Backed Rankings
MISO is the richest market in the US for evidence-backed developer rankings. The top 10 by solar MW among Load Factor's highest-rated attributions in this MISO snapshot:
| Rank | Developer | Solar Projects | Solar MW |
|---|---|---|---|
| 1 | NextEra Energy | 23 | 5,353.8 |
| 2 | DTE Energy | 27 | 4,230.3 |
| 3 | Entergy | 14 | 3,389.0 |
| 4 | Xcel Energy | 17 | 2,784.0 |
| 5 | Doral Renewable | 9 | 2,295.0 |
| 6 | Apex Clean Energy | 7 | 2,205.5 |
| 7 | Recurrent Energy | 11 | 1,997.0 |
| 8 | Ranger Power | 9 | 1,848.6 |
| 9 | RWE | 11 | 1,828.0 |
| 10 | Treaty Oak | 6 | 1,815.0 |
Source: Load Factor's highest-rated attributions (its top confidence labels) in this snapshot, MISO solar; those labels are being re-graded against the two-source rule, so read the ranking as indicative.
The leaderboard is not monopolistic. The top MISO solar developer (NextEra at 5,353.8 MW) is substantial, but behind it is a deep field spanning utility-affiliated names, national IPPs, and mid-size platforms. MISO solar is a multi-player market.
For the full analysis including geographic breakdown and evidence methodology, see the most active MISO solar developers post.
Why MISO Has the Best Developer Intelligence of Any Major US ISO
MISO's developer identification coverage is significantly deeper than PJM or CAISO for several structural reasons:
Grid-operator transparency. MISO publishes more project-level detail than most grid operators, which gives every attribution a firmer starting point.
Geographic breadth and evidence depth. MISO's 13-state footprint covers states with accessible public records, and Load Factor's state and county evidence coverage is deepest in MISO territory.
Operating-plant density. MISO states have meaningful operating plant density, so federal plant records often add an independent second source for queue-level attributions.
Together, grid-operator, federal, state and county public records create the multi-source environment that MISO's developer attributions are built on.
How to Use MISO Queue Data
For developers: MISO's depth makes it the best market for competitive positioning analysis. You can identify which developers are accumulating solar MW in specific states and counties, and cross-reference their queue positions against the cited evidence.
For investors and lenders: MISO's evidence depth means you can verify developer claims with cited sources - not editorial assignments. A developer claiming MISO portfolio positions can be cross-checked against the cited public records in minutes.
For advisors: MISO provides more reliable developer data for competitive landscape analysis than any other major ISO. Rankings built from MISO data are defensible in client presentations.
Frequently Asked Questions
How many projects are in the MISO interconnection queue?
As of March 2026, Load Factor tracked 5,545 MISO queue projects, the second-largest ISO total after PJM's 10,875.
What fuel types dominate MISO's interconnection queue?
As of March 2026, solar led with 1,912 projects and 304,523.7 MW. Wind followed with 1,523 projects. Battery storage has grown to 839 standalone applications totaling 122,434.5 MW.
Which states have the most MISO solar projects?
Arkansas leads by MW (52,739.5 MW), followed by Louisiana (39,726.7 MW) and Indiana (36,237.7 MW). Illinois and Michigan are close behind.
How many MISO developers has Load Factor identified?
As of March 2026, 3,938 projects had developer identification, each with its confidence level and sources. 1,607 remained unknown pending additional evidence.
How do I browse MISO projects on Load Factor?
Filter by MISO on the Browse page. Filter further by fuel type, state, county, developer, or evidence level. No account required for the public layer.