Figures on this page are from Load Factor’s queue data as of May 2026. Live totals, withdrawn requests included, are on the coverage page.
Battery storage is no longer a footnote to the solar story in US interconnection queues. It has become one of the central narratives.
Load Factor's current database includes 9,564 standalone battery storage projects totaling 1,557,878.7 MW of queued BESS capacity across 16 North American markets. When hybrid solar-plus-storage projects are added, the total storage-adjacent queue exceeds 10,400 applications and 1.66 trillion watts of intended capacity.
That scale matters for everyone who touches the development, financing, or analysis of energy storage projects - because the queue is where the buildout becomes visible before it becomes a deal.
Where Battery Storage Is Concentrating in US Interconnection Queues
Standalone battery storage in US interconnection queues is not evenly distributed. It is concentrated in specific regional markets with distinct economic drivers.
| ISO / Market | Storage Projects | Storage MW |
|---|---|---|
| West (non-CAISO) | 2,762 | 610,892.5 |
| ERCOT | 1,540 | 246,279.3 |
| CAISO | 1,099 | 239,020.5 |
| MISO | 842 | 122,434.5 |
| SPP | 653 | 113,412.8 |
| PJM | 1,414 | 104,796.9 |
| Southeast | 715 | 89,207.5 |
| NYISO | 427 | 54,400.8 |
The headline concentration is in ERCOT and CAISO - Texas and California have been the center of gravity for utility-scale BESS for years. But the story has moved substantially. The Western non-CAISO markets have now eclipsed CAISO in total project count, and MISO, SPP, PJM, and NYISO all carry storage application volumes that can no longer be treated as secondary.
Battery Storage by State: Texas and California Lead, but the Map Is Wider
| State | Storage Projects | Storage MW |
|---|---|---|
| Texas | 1,647 | 265,719.5 |
| California | 1,139 | 233,492.5 |
| Arizona | 532 | 153,110.0 |
| Oregon | 482 | 106,077.5 |
| Nevada | 352 | 102,155.5 |
| Utah | 367 | 61,085.0 |
| Washington | 272 | 59,187.5 |
| New York | 411 | 49,420.8 |
| Idaho | 197 | 39,367.5 |
| New Mexico | 208 | 38,528.9 |
Arizona, Oregon, and Nevada each exceed 100,000 MW of queued storage capacity - numbers that few market summaries reflect. New York has become a meaningful BESS market. The geography of US storage development has expanded well beyond the Texas-and-California narrative that dominated early BESS commentary.
The Post-2021 Battery Storage Acceleration
Queue-year data shows exactly when battery storage shifted from a niche category to a mainstream queue strategy.
| Queue Year | Storage Projects | Storage MW |
|---|---|---|
| 2018 | 378 | 47,680.0 |
| 2019 | 695 | 88,583.8 |
| 2020 | 802 | 109,051.5 |
| 2021 | 1,376 | 243,874.8 |
| 2022 | 1,388 | 245,229.9 |
| 2023 | 1,231 | 263,107.7 |
| 2024 | 1,147 | 201,690.4 |
| 2025 | 1,103 | 230,522.5 |
The inflection in 2021 is not subtle. Annual storage applications roughly doubled from 2020 to 2021 and held at that level through 2025. The IRA's transferability provisions, falling battery costs, and merchant revenue opportunities in ERCOT and CAISO all contributed. The queue sustained four-digit annual storage application counts across five consecutive years.
That pattern means the storage buildout is not a spike - it is a sustained structural shift in how developers are using interconnection queues.
Hybrid Storage: A Separate and Growing Battery Queue Category
Load Factor also tracks 927 hybrid projects - solar-plus-storage, wind-plus-storage, and other multi-fuel applications - totaling 103,399.7 MW. This category matters separately because hybrid queue strategy is different from standalone BESS:
- Revenue stacking: Hybrid applications allow developers to optimize across energy, capacity, and ancillary service revenues simultaneously
- Interconnection economics: In some markets, a hybrid application can access a different queue pathway or cost structure
- Siting logic: Co-locating storage with existing or proposed solar can reduce interconnection cost
MISO and PJM both show substantial hybrid volume - 68,223.3 MW and 35,176.3 MW respectively in the current snapshot.
Who Is Developing Battery Storage Projects
The developer identification picture for battery storage is similar to the broader queue: most projects are filed by SPVs and LLCs that require forensic research to connect to their actual sponsors.
What Load Factor finds consistently in the storage evidence pipeline:
- The largest standalone BESS applications in ERCOT are frequently connected to well-known merchant storage developers, infrastructure funds, and utilities through federal filings and plant records
- CAISO's storage applications include a mix of solar developer-affiliated storage projects and pure merchant BESS platforms
- PJM storage attribution is harder - the developer identification gap in PJM (4,229 unknowns out of 10,875 total projects) extends to the storage subset
- MISO storage offers stronger attribution because MISO's transparency and the evidence pipeline's depth allow more confident identification
For the specific developer-level breakdown in MISO and the broader methodology, see how Load Factor identifies developers and the battery storage queue analysis.
What the Storage Queue Tells You Before the Deals Do
Most deal databases capture storage transactions after they are announced. That information is useful for benchmarking and market analysis.
The queue tells you something different and earlier: where developers are trying to interconnect storage, how large their applications are, and which of those applications are connected to identifiable sponsors. A storage developer with well-evidenced queue positions in multiple ISOs and a track record of project completion looks different from one with a single pending application and no evidence trail.
Load Factor covers both the queue layer and the deal layer. When a storage developer closes a transaction, that deal enters Load Factor's database alongside their existing queue positions.
Frequently Asked Questions
How many battery storage projects are in US interconnection queues?
As of May 2026, Load Factor's database included 9,564 standalone battery storage projects totaling 1,557,878.7 MW. Adding 927 hybrid projects brought the storage-adjacent total above 10,400 applications.
Which ISO has the most battery storage applications?
As of May 2026, by project count, the Western markets (non-CAISO) led with 2,762 projects. ERCOT follows with 1,540, PJM with 1,414, and CAISO with 1,099. By MW, the West's 610,892.5 MW exceeds all individual ISOs.
Are all queued battery storage projects going to be built?
No. The interconnection queue is a development pipeline, not a construction forecast. Many projects are withdrawn before reaching commercial operation. The withdrawal rate varies significantly by ISO - PJM's overall withdrawal rate is 67%. The queue is most useful as a signal of developer interest and investment concentration, not as a built-capacity forecast.
What states have the most battery storage applications?
As of May 2026, Texas (1,647 projects, 265,719.5 MW) and California (1,139 projects, 233,492.5 MW) led. Arizona, Oregon, Nevada, and Utah each exceed 100 GW of queued storage capacity.
How do I find which developer controls a battery storage project?
Search the Load Factor Browse interface and filter to any ISO, state, or county. Projects with an identified developer show the developer name, evidence count, and confidence level. Projects with no developer identified show the entity name from the queue filing.
Filter all BESS projects by ISO and state | See developer evidence methodology | Read: Battery Storage Is Flooding US Queues
See also: ERCOT Queue (largest named ISO for BESS) | MISO Queue | US Queue by the Numbers