Oklo has asked FERC to force PJM to reinstate a 750 MW project that PJM withdrew from its first reformed interconnection cycle. Filed as docket EL26-101-000 in late August, the complaint is the first legal stress test of PJM's reformed cluster-study rules on a multi-fuel hybrid plant, and the outcome could set the precedent for how every RTO models hybrid generation.
The project, identified only as queue number C01-1735, combines 150 MW of advanced nuclear, 300 MW of fuel cells, and 300 MW of natural gas. Oklo entered it into PJM's Cycle 01 on April 27, 2026. PJM issued a deficiency notice on May 15 and withdrew the project on August 3, saying it failed stability requirements and flagging discrepancies between its modeling files and PQ curves.
| Category | Capacity (MW) |
|---|---|
| Advanced nuclear | 150 |
| Fuel cells | 300 |
| Natural gas | 300 |
Source: Oklo FERC complaint, docket EL26-101-000
Oklo's core claim: PJM applied a low-voltage ride-through stability test meant for inverter-based resources to the entire facility, even though only the fuel-cell component is inverter-based. PJM's own modeling guidelines, Oklo argues, require fault testing only for inverter-based resources. PJM has called its decision final and does not comment on individual applications.
The stakes are concrete. Oklo says the withdrawal delays the project by at least 14 months and raises development costs. It asked FERC to fast-track the case, require PJM's answer by September 4, and reinstate the project before Cycle 01 Phase I studies begin September 28. PJM says 90% of the 811 new service requests in Cycle 01 cleared the first round of review.
Why this matters: multi-fuel hybrids are no longer a corner case. Load Factor's queue data shows 148 hybrid projects currently in PJM's interconnection queue, out of 2,131 total. These plants pair synchronous machines (nuclear, gas) with inverter-based resources (fuel cells, storage) as the standard playbook for firm 24/7 power for data centers. But interconnection study templates were built for single-technology projects. If FERC sides with Oklo, RTOs nationwide will need procedures that model mixed-technology plants as they actually behave.
| Category | Projects |
|---|---|
| Solar | 1,308 |
| Battery Storage | 383 |
| Wind | 231 |
| Hybrid | 148 |
| Hydro | 33 |
| Offshore Wind | 16 |
| Biomass | 10 |
| Wood | 2 |
Source: Load Factor Developer Tracker, September 2026
Utility Dive has tied the queue entry to Oklo's planned 1.2 GW Pike County, Ohio campus, announced in January to supply Meta data centers, though Oklo's complaint redacts the project's identity and location. Consistent with that redaction, the project does not appear by name in Load Factor's tracker data.
What to watch: whether FERC rules before the September 28 Phase I start, and whether the ruling reaches beyond Oklo's reinstatement to the broader question of hybrid modeling standards. We are tracking EL26-101-000 and will update this briefing as the docket moves.