The Southwest Power Pool moves more wind energy as a share of its load than any other US electricity market. In 2023, SPP set a record by serving 105% of its load from wind for a brief period โ the first time any major US grid exceeded 100% wind penetration. Yet SPP's interconnection queue tells a story that is rapidly shifting away from wind-only dominance.
Load Factor tracks 2,830 active projects in SPP's queue across Kansas, Oklahoma, Nebraska, South Dakota, and adjacent states. That queue reflects both the legacy wind economy and the emerging solar and storage wave reshaping the Plains energy landscape.
SPP's Queue at a Glance
SPP administers interconnection across a 14-state footprint stretching from Montana to Texas, though the bulk of its generation queue is concentrated in the central states. Key characteristics of the current queue:
| State | Dominant Fuel Type | Queue Maturity |
|---|---|---|
| Kansas | Wind (legacy), Solar (new) | Deep โ large operating wind base |
| Oklahoma | Wind + Solar | Active โ new solar applications accelerating |
| Nebraska | Wind + Solar | Growing โ IRA incentives driving solar |
| South Dakota | Wind | Moderate โ limited solar economics |
| North Texas | Mixed (overlaps ERCOT border) | Complex โ SPP/ERCOT boundary projects |
The LBNL "Queued Up" 2024 report shows SPP with more than 200 GW of pending generation capacity in its queue, with solar now representing the plurality of new applications by MW. Wind remains the largest operating fuel category within SPP's footprint, but the pipeline is transitioning.
The Wind Legacy and Why It Still Matters
To understand SPP's queue, you have to understand the wind economy that built it. Kansas and Oklahoma rank among the top five US states for installed wind capacity. NextEra Energy Resources, Enel Green Power, Invenergy, and Apex Clean Energy collectively account for a large share of operating wind in SPP's footprint โ most of it built between 2008 and 2020 under production tax credit (PTC) economics.
That operating fleet shapes the queue in two ways. First, wind repowering projects โ replacing aging turbines with more efficient models at existing interconnection points โ are a growing segment of SPP's current applications. Repowered projects can often retain their existing interconnection agreements, making them lower-risk than greenfield applications. Second, transmission capacity that was built to serve large wind farms in western Kansas and the Oklahoma Panhandle creates available headroom for new solar and storage projects along the same corridors.
The PTC phase-down and eventual replacement by IRA technology-neutral clean energy tax credits has modestly reduced the PTC advantage that made wind economics so compelling in SPP. New applications now weigh wind and solar returns against the same baseline incentive structure.
Solar's Entry Into SPP's Queue
Solar applications in SPP have grown significantly since 2021. The drivers include:
- Falling module costs. Utility-scale solar LCOE in the central US has fallen below wind LCOE at many sites due to continued module cost reductions, even without accounting for the IRA's domestic content bonus.
- Load growth from data centers and industrials. Oklahoma and Kansas have attracted data center development, creating corporate PPA demand for large-scale solar within SPP's footprint.
- State-level policy signals. Kansas's property tax exemption for renewable energy equipment and Oklahoma's zero-emission tax credit have improved project economics for solar developers entering these markets.
- Lower community opposition than wind. Large-scale solar faces less organized opposition in agricultural communities across the Plains than utility-scale wind, reducing development timeline risk.
Battery storage applications in SPP lag behind ERCOT and CAISO. SPP's market design does not create the same merchant BESS revenue stack that exists in ERCOT's energy-only market. Storage applications in SPP are predominantly co-located with solar under hybrid project structures that can claim the IRA storage ITC.
Who Is Developing in SPP?
Developer identification in SPP follows the same evidence chain that applies across other ISOs: Secretary of State LLC registrations, FERC interconnection agreements, EIA-860 ownership disclosures, and project-level news. The Plains states are generally straightforward for developer research โ Kansas and Oklahoma SoS portals have reasonable public access, and the relatively concentrated developer community means projects cluster around a recognizable set of operators.
The largest active developers in SPP's queue include both independent power producers (IPPs) who build and sell, and utilities with integrated development programs. Several factors make SPP developer identification tractable:
- SPP publishes its Generation Interconnection Queue with developer names for most active projects, unlike some ISOs that redact applicant identities
- Kansas and Oklahoma SoS registrations are accessible and searchable, allowing LLC-level verification of project ownership
- FERC GIA filings for executed agreements provide authoritative developer identification with counterparty data
- The operating wind fleet creates a known developer map that new solar and storage applicants often follow โ same developers, new fuel types
SPP's Interconnection Process and Reform Impact
SPP has historically processed interconnection through a serial study methodology similar to other ISOs. Under FERC Order 2023, SPP is transitioning to a cluster-based approach for new applications received after July 2024. This change will affect how the current SPP queue backlog is processed.
SPP's queue has experienced significant withdrawal rates, consistent with national patterns. The LBNL "Queued Up" 2024 report finds that roughly 75โ80% of projects that enter US interconnection queues ultimately withdraw before reaching commercial operation. SPP's wind-heavy history means many older applications in its queue represent projects from earlier study cycles that have since been superseded by better-sited or better-capitalized competitors.
For new applicants, the cluster reform means entering a study group where interconnection costs are allocated across multiple projects simultaneously. Early indications from MISO's cluster experience suggest that study cycle timelines may lengthen initially before improving as the methodology matures. SPP applicants entering the queue in 2025 and 2026 should expect multi-year study cycles before receiving final interconnection cost estimates.
Why This Matters for Developers and Investors
SPP's queue is often overlooked in favor of larger-volume markets like PJM and CAISO, but it offers structural advantages for certain development strategies:
- Lower land cost. Agricultural land in Kansas and Oklahoma remains among the lowest-cost development acreage in the US, supporting project economics that are harder to achieve in coastal markets.
- Available transmission. The wind build-out created transmission infrastructure in corridors that can support new solar and storage projects without the full greenfield transmission investment required in constrained markets.
- Corporate PPA demand. Oklahoma City's growing tech and data center economy, and Kansas City's industrial base, represent growing offtake demand for large-scale renewable PPAs within SPP's footprint.
- Developer consolidation opportunity. SPP has a higher proportion of smaller independent developers than CAISO or PJM. This creates M&A opportunity for larger platforms seeking to acquire late-stage projects in a cost-effective market.
For investors tracking developer activity in SPP, the combination of legacy wind operator knowledge and new solar application volume creates a dynamic where developer identification โ knowing who is behind each project โ becomes a meaningful research edge. The same LLC structures used for MISO and ERCOT wind development often appear in SPP's solar pipeline.
Conclusion
SPP's queue, 2,830 projects as of April 2026, reflects a Plains energy market in transition โ from wind-only dominance toward a solar-and-storage future that shares its transmission infrastructure with the wind economy that preceded it. Developer concentration, accessible state registration data, and growing corporate PPA demand make SPP a tractable market for developer identification research.
For the wind-versus-solar context that frames SPP's queue dynamics, see Wind vs. Solar in US Interconnection Queues. For the broader withdrawal-rate context that shapes how many SPP projects will actually reach commercial operation, see Interconnection Queue Withdrawal Rates: What Withdrawn Projects Reveal.
Load Factor tracks all 2,830 SPP queue projects with developer identification, evidence chains, and geographic data. Browse SPP projects to see the current queue.