A Generator Interconnection Agreement - a GIA - is one of the most authoritative public documents available for renewable energy project research. It is a contract between the developer's project entity, the transmission owner, and the regional transmission organization. It names the project sponsor explicitly. It includes the interconnection point, the contracted capacity, and the cost allocation for network upgrades. And it is filed publicly with FERC.

For queue intelligence purposes, a GIA is about as strong as public evidence gets: a signed agreement, filed with a federal regulator, that names the legal entity behind a queue position.

Here is how to find them and what to do with them.

What a GIA is and when it exists

A GIA is executed after a project completes the interconnection study process and reaches a binding agreement with the transmission owner and ISO/RTO. The study process typically takes two to four years. Projects that reach a GIA have passed the technical and cost-allocation review - they are serious projects with substantial development investment behind them.

Not every queue project has a GIA. The majority of queue entries are in study or pre-study phases. Projects that have been withdrawn never reach GIA stage. The subset with executed GIAs is smaller than the full queue but represents the most advanced and creditworthy project population.

For anyone researching the company behind an SPV, an executed GIA is one of the strongest records there is. If one exists, much of the research question is answered.

Where FERC GIAs are filed

FERC requires transmission owners and ISOs to file executed GIAs with the Commission under FERC's tariff filing requirements. The documents are accessible via FERC's eLibrary, which is publicly available without registration.

eLibrary search: https://elibrary.ferc.gov/eLibrary/search

The relevant docket categories for GIA filings:

Docket typeWhat it covers
ER (Electric Rate)Most GIAs are filed under ER dockets by the transmission owner
EL (Electric)Some interconnection-related cases, particularly complaint proceedings
QF (Qualifying Facility)Smaller projects (often under 20 MW) that qualify as PURPA facilities

GIAs are typically filed as tariff sheets or as attachments to tariff filings. They appear under the transmission owner's FERC docket, not under a project-specific docket.

How to search for a GIA by project

Because GIAs are filed by the transmission owner (not the project developer), a direct project name search is the most effective approach.

Step 1: Search by project name. Go to FERC eLibrary and search for the project SPV name or the project's common name. If the GIA has been filed, the document will typically appear in eLibrary with the SPV name in the document text.

Step 2: Search by queue number. Some ISOs include queue numbers in their GIA filings. Searching the queue number directly (e.g., "ERCOT Q-2021-0145" or "PJM Queue X5-186") may return the relevant filing.

Step 3: Search by transmission owner + date range. If you know which transmission owner covers the project's area, filter by the transmission owner company name and a date range that covers the likely GIA execution period.

Step 4: Check ISO websites. Some ISOs publish executed GIA summaries or lists separately from FERC. MISO publishes a Generator Interconnection Agreement log. PJM has its own docket filing system (eTariff) that mirrors FERC filings.

What a GIA contains: key fields for project research

GIAs follow a standard structure required by FERC's pro forma interconnection tariff. The following sections are the most useful for developer identification and project intelligence.

Project identification (Article 1 or recitals)

The opening recitals name:

  • The Interconnection Customer - the SPV name, usually with its state of formation
  • The Transmission Owner - the utility or transmission company that owns the network
  • The Transmission Provider - the ISO/RTO (e.g., MISO, PJM, ERCOT)
  • The Generating Facility - the project's common name, location (county/state), and fuel type
  • The Point of Interconnection - the specific substation and voltage level where the project connects

This section resolves the SPV question: the Interconnection Customer is the legal party to the agreement. Who stands behind that SPV is a separate question, and it usually takes more than one public record to answer.

Technical specifications (Exhibit A)

Exhibit A describes the generating facility in technical detail:

  • Nameplate capacity (MW AC and DC for solar)
  • Generator technology (single-axis tracking, BESS chemistry, turbine model)
  • Interconnection voltage
  • NERC function list - whether the project will operate as a generator under NERC reliability standards

This section is the authoritative source for project MW size. Queue applications sometimes use planning numbers that change during study; the GIA reflects the negotiated contracted capacity.

Network upgrades (Exhibit B)

Exhibit B lists the transmission network upgrades required to accommodate the project's injection. This is where interconnection costs are documented.

Key items:

  • Upgrade list - each transmission system upgrade (line rebuilds, substation expansions, switching equipment) with cost estimates
  • Cost responsibility - the developer's share vs. the transmission owner's share
  • Affected system upgrades - upgrades on neighboring systems triggered by the project

For investors and lenders, the Exhibit B cost allocation is critical financial information. Large network upgrade obligations can materially affect project economics.

Commercial operation date (Article 3 or 4)

The GIA specifies the anticipated commercial operation date (COD) and the study milestones. This date is the developer's contracted target, not a guarantee. Delays are common. But the GIA COD provides a baseline for tracking project progress.

Load Factor shows GIA execution dates and CODs on the project where they are available.

Default and termination provisions

The GIA specifies the conditions under which the interconnection agreement can be terminated - typically developer default, project cancellation, or failure to meet milestone obligations. These provisions matter for downstream tracking of whether an advanced project is still viable.

FERC GIA filings and ERCOT: an important limitation

ERCOT is a notable exception to the FERC GIA pattern. Because ERCOT is not subject to FERC jurisdiction for its energy market (it operates within a single state), ERCOT interconnection agreements are not filed with FERC the way PJM or MISO GIAs are.

ERCOT Generator Interconnection Agreements are governed by ERCOT's NODAL Protocols and filed with the Public Utility Commission of Texas (PUCT), not FERC. To find ERCOT GIA-equivalent documents, the relevant search is:

  • PUCT Interchange: The PUCT's docket system contains ERCOT filings, including interconnection-related matters
  • ERCOT GIS Report: ERCOT's public GIS Report tracks project status milestones including GIA execution dates
  • Direct ERCOT requests: Some interconnection agreement details require direct data requests from ERCOT

So for ERCOT projects, other public records have to carry the weight that a FERC filing carries in PJM or MISO - which makes ERCOT's developer coverage in Load Factor all the more a product of Texas's unusually consistent public records.

Reading a GIA: a practical example walkthrough

A typical GIA for a 250 MW solar project in the PJM footprint looks like this:

Recitals:

This Generator Interconnection Agreement is entered into as of [date] between Summit Solar Delaware LLC, a Delaware limited liability company ("Interconnection Customer"), and Allegheny Power Service Corporation ("Transmission Owner"), and PJM Interconnection, LLC ("Transmission Provider").

From this one section you learn:

  1. The SPV is Summit Solar Delaware LLC, a Delaware LLC
  2. The developer is likely operating in PJM's Allegheny Power territory
  3. The transmission owner is Allegheny Power

Exhibit A:

Generating Facility: 250 MW (AC) / 312 MW (DC) single-axis tracking photovoltaic facility located in Fayette County, Pennsylvania.

Now you know the project is in Fayette County, PA - which tells you whose local public records cover the site.

Exhibit B:

Network Upgrade 1: Rebuild 4.6 miles of 115 kV line on the Uniontown-Leisenring circuit - estimated cost $14.2M, Interconnection Customer responsibility: 100%.

The $14.2M upgrade obligation is financial information that affects project viability.

These three sections together - project identity, location, and cost obligation - provide more actionable intelligence than any queue record summary.

How Load Factor uses GIA data

Interconnection agreements are federal regulatory filings, one of the many kinds of public record Load Factor reads. Like every other source, an agreement appears on the project it supports, with a link to the public record it came from. A developer shows Two sources agree only when two or more independent primary sources name it, and an executed agreement is often one of them.

FERC-filed agreements cover PJM, MISO and the other FERC-jurisdictional markets. For ERCOT, and for markets where state regulators hold the agreements, other public records fill the gap.

Frequently Asked Questions

What is a FERC Generator Interconnection Agreement? A GIA is a contract between a power project developer (via their SPV), the local transmission owner, and the ISO/RTO that governs how the new generator will connect to the transmission grid. It is executed after the interconnection study process and filed publicly with FERC.

Are FERC GIA filings publicly available? Yes. GIAs are filed by transmission owners under FERC tariff dockets and are searchable via FERC's eLibrary at elibrary.ferc.gov. No registration is required for search and document retrieval.

What information in a GIA is useful for identifying a project's developer? The recitals section names the Interconnection Customer (the project SPV), the transmission owner, and the ISO/RTO. Exhibit A describes the technical specifications and location. Read together with other public records, that is often enough to see who stands behind the SPV.

Does ERCOT file GIAs with FERC? No. ERCOT operates under Texas jurisdiction, not FERC jurisdiction for its energy market. ERCOT interconnection agreements are filed with the Public Utility Commission of Texas (PUCT), not FERC. ERCOT GIA-equivalent research requires PUCT docket search or ERCOT GIS Report data.

What is the difference between an interconnection agreement and an interconnection study? A study is the technical analysis performed to determine what upgrades are needed and at what cost. An agreement is the executed contract that follows a successful study. Many projects complete studies but withdraw before executing an agreement. A GIA indicates a project has committed to the cost allocation and moved forward.

Methodology

Interconnection agreements are federal regulatory filings, one of the many kinds of public record Load Factor reads. FERC-filed agreements cover PJM and MISO; ERCOT's equivalents sit with the Public Utility Commission of Texas. Attribution confidence is described in Who Is Behind That SPV?. Load Factor does not redistribute FERC document text; it records attribution metadata derived from public filings.

Conclusion

A FERC GIA is the closest thing renewable energy project research has to a primary source. It names the parties, specifies the project, and documents the financial obligations in a single public document. Learning to find and read them - through FERC eLibrary, ISO tariff portals, and state PUC systems for non-FERC jurisdictions - is a foundational skill for queue analysis.

Browse queue projects to see the developer and the evidence behind each one. For the broader SPV tracing methodology, read What Is an SPV in Renewable Energy? and Who Is Behind That SPV?.

Share this

Load Factor tracks 38,000+ interconnection queue projects, withdrawn included, across 16 North American markets, with the evidence behind every developer it names.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues

Book a 30-min walkthrough