On September 21, North Carolina regulators denied Duke Energy a permit for a 250-MW gas turbine meant to power Amazon's $10 billion data center campus. Three Republican appointees voted no. Duke's load forecast was unvetted, nobody showed data centers would pay, and the plant clashed with the White House Ratepayer Protection Pledge. The turbines are sold out, the queues are filling with gas, and now the politics of who pays is the gating item.
The numbers behind the comeback:
| GW | GW |
|---|---|
| Natural gas | 105.8 |
| Storage | 67.5 |
| Nuclear | 17.9 |
| Solar | 14.8 |
| Solar+storage hybrid | 8.9 |
| Wind | 4.7 |
Source: PJM
- Gas queue capacity jumped 86% in 2025, after 72% in 2024, while solar, wind, and storage entries all shrank (LBNL).
- PJM's first reformed queue cycle drew 220 GW of requests. Gas was the largest fuel at 105.8 GW across 157 projects, about 48% of the total.
- MISO's fast-lane queue class is roughly 70% gas. In ERCOT, monthly gas queue entries tripled after the OBBBA.
| Category | % |
|---|---|
| 2024 | 72 |
| 2025 | 86 |
Source: LBNL
- The equipment is gone. GE Vernova holds 116 GW of turbine orders and reservations and is taking reservations for 2031 delivery. Siemens Energy holds 87 GW with waits up to four years.
- PJM's December capacity auction missed its reliability target for the first time ever. Data center load forecasts drove about 40% of the $16.4 billion cost.
Two tracks, one grid. Renewables and storage still dominate queue volumes, but gas is the only fuel growing, it moves through queues faster, and it clears 43 to 45% of PJM capacity auctions against about 1% for solar. The build signal is the strongest in PJM history. The binding constraints are now physical (turbines) and political (who pays).
What to watch: FERC's large-load tariff rulings after the June show-cause orders, the uncapped PJM capacity auction, and whether more states follow North Carolina in making data centers prove they will pay.
Sources
- LBNL, "Queued Up" 2026 edition (US interconnection queue data): https://emp.lbl.gov/queues
- POWER Magazine, "PJM's First Reformed Queue Cycle Draws 811 Projects, 220 GW" (April 2026): https://www.powermag.com/pjms-first-reformed-queue-cycle-draws-811-projects-220-gw/
- Carbon Direct, "AI Meets the Grid" white paper (May 2026): https://www.carbon-direct.com/research-and-reports/ai-meets-the-grid-interconnection-queue-analysis-in-pjm-and-ercot
- GE Vernova Q2 2026 earnings press release (turbine backlog): https://files.quartr.com/reports/bbfb6eec15007776b86e9cd92a1a37ce-2026-07-22-10-24-10.pdf?ref=U0E=
- Siemens Energy gas turbine backlog analysis (2026): https://www.ad-hoc-news.de/boerse/news/ueberblick/siemens-energy-s-record-backlog-creates-a-four-year-wait-and-a-test/69531463
- PJM, 2026/27 Base Residual Auction results (July 2025): https://insidelines.pjm.com/pjm-auction-procures-134311-mw-of-generation-resources-supply-responds-to-price-signal/
- PJM, 2027/28 Base Residual Auction results (December 2025): https://www.morningstar.com/news/pr-newswire/20251217ph50285/pjm-auction-procures-134479-mw-of-generation-resources
- Public Radio East, "NC Utilities Commission denies Duke Energy gas plant" (Sept 21, 2026): https://www.publicradioeast.org/2026-09-21/nc-utilities-commission-denies-duke-energy-gas-plant
- RTO Insider, "MISO Accepts 6 GW of Gas Gen in 2nd Queue Fast Lane Class": https://rtowww.com/120857-miso-accepts-6gw-gas-gen-2nd-queue-fast-lane-class/
- Bracewell via JDSupra, "FERC Issues Show Cause Order on Large Loads" (June 2026): https://www.jdsupra.com/legalnews/ferc-issues-show-cause-order-on-large-6716941/