Battery Storage Is Flooding US Interconnection Queues: Where and How Much

Published April 28, 2026 • 6 min read • Load Factor team
Share this

Battery storage is no longer a supporting detail in US interconnection queues. It is one of the main events.

In Load Factor's current working snapshot, the queue includes 9,564 standalone storage projects when Battery Storage and Storage labels are combined. Add another 927 Hybrid projects, and the storage buildout becomes impossible to dismiss as a solar footnote. Storage is now a queue-wide application pattern with its own regional map, its own backlog dynamics, and its own commercial logic.

That shift matters because queue data is often the first place a storage wave becomes visible. By the time project sales, financing announcements, or offtake structures make headlines, the queue has usually been signaling the buildout for months or years.

The biggest storage queues are not evenly distributed

Standalone storage is highly concentrated by ISO and regional market. In the current Load Factor rollup, the largest storage queues are:

ISO / MarketStandalone storage projectsStandalone storage MW
West2,762610,892.5
ERCOT1,540246,279.3
CAISO1,099239,020.5
MISO842122,434.5
SPP653113,412.8
PJM1,414104,796.9
Southeast71589,207.5
NYISO42754,400.8

Two patterns stand out immediately.

First, storage is not confined to California and Texas. ERCOT and CAISO are still central, but MISO, SPP, PJM, and the Southeast all carry meaningful storage application volume.

Second, storage MW is concentrating in a few regions faster than many market summaries imply. The West grouping alone exceeds 610,000 MW in the current rollup. ERCOT and CAISO together add another 485,299.8 MW. That is not a marginal category. It is a core buildout signal.

The state map is led by Texas and California, but it does not stop there

At the state level, storage concentration is clearer still.

StateStandalone storage projectsStandalone storage MW
Texas1,647265,719.5
California1,139233,492.5
Arizona532153,110.0
Oregon482106,077.5
Nevada352102,155.5
Utah36761,085.0
Washington27259,187.5
New York41149,420.8
Idaho19739,367.5
New Mexico20838,528.9

Texas and California are the obvious leaders, but the deeper story is how quickly the next tier rises. Arizona, Oregon, and Nevada each carry more than 100,000 MW in the current storage rollup. New York is now part of the meaningful storage conversation. Illinois, Virginia, Indiana, Georgia, and Michigan all show substantial counts as well.

This is not just a sunbelt-plus-California pattern. It is a multi-market storage wave with different commercial drivers in each region: energy arbitrage, capacity value, renewable integration, transmission constraints, and data-center-related demand in some submarkets.

Storage queue growth accelerated sharply after 2018

The queue-year trend shows how quickly BESS moved from niche category to mainstream queue strategy.

Queue yearStandalone storage projectsStandalone storage MW
201837847,680.0
201969588,583.8
2020802109,051.5
20211,376243,874.8
20221,388245,229.9
20231,231263,107.7
20241,147201,690.4
20251,103230,522.5

The inflection is obvious. Storage did not just grow gradually. It stepped up into a new scale beginning in 2021, then sustained four-digit annual project counts through 2025.

That matters because queue-year growth tells you something different from cumulative queue size. Cumulative size can reflect legacy backlog. Queue-year growth tells you whether developers are still choosing storage as a preferred application pathway now. In the storage data, the answer is clearly yes.

Hybrid storage is a separate category and should be treated that way

Not every storage-heavy queue position is a standalone BESS project.

Load Factor's current snapshot also shows:

  • 927 hybrid projects
  • 103,399.7 MW of hybrid capacity

Hybridization is especially relevant in markets where storage is being paired with solar to improve revenue shape, capacity value, curtailment management, or interconnection economics. MISO and PJM stand out here. In the current rollup, MISO hybrid projects total 68,223.3 MW and PJM hybrids total 35,176.3 MW.

This is why any serious battery storage interconnection queue analysis has to keep three buckets separate:

  1. Standalone storage.
  2. Solar-plus-storage or other hybrid projects.
  3. Solar projects that may later add storage but are not yet filed as hybrid.

Lumping them together inflates some markets and hides what developers are actually filing.

Storage's strategic value is now showing up before deal flow

One reason queue-level storage analysis matters is that it gets ahead of the headlines. Enerdatics and similar platforms are strong on transaction coverage after assets move into sale, finance, or portfolio commentary. The queue tells you where storage interest is building before that.

That is where Load Factor's model is different. The question is not simply "how many storage deals closed?" It is "where are developers trying to interconnect storage, how large are those applications, and which queue positions are tied to identifiable sponsors versus opaque project shells?"

The storage answer is increasingly cross-regional:

  • ERCOT remains a core storage market.
  • CAISO is still one of the most storage-heavy queues in the country.
  • Western markets beyond California now matter at scale.
  • MISO, SPP, and PJM are no longer secondary in storage discussion.

What the storage queue is really signaling

The storage queue is signaling three things at once.

First, developers increasingly view storage as a primary project type, not just an enhancement to solar. The standalone counts prove that.

Second, developers are using storage in multiple market roles. In some regions it is a congestion and flexibility play. In others it is a capacity and revenue-shape play. In still others it is a companion strategy to solar clustering.

Third, storage competition is becoming geographic rather than generic. The next question is not whether storage is growing. It is where the applications are densest, which counties and substations are attracting them, and which developers are repeatedly showing up in those clusters.

Methodology

This post uses Load Factor's canonical product context of 38,000+ queue projects, withdrawn included, across 16 ISOs and power markets. Storage-specific distributions come from the current PostgreSQL project snapshot. Standalone storage combines rows where fuel_type is Battery Storage or Storage. Hybrid is kept separate. Capacity totals use summer_mw with winter_mw fallback where needed. Queue-year analysis uses the normalized queue_year field and should be interpreted as directionally useful application timing rather than a final construction forecast.

Conclusion

Battery storage is not arriving at the edge of the interconnection queue. It is reshaping the center of it. The counts are large, the MW is larger, and the geography is wider than the usual Texas-and-California shorthand suggests.

If you want to inspect the underlying BESS records, search battery storage projects across all 16 ISOs on Load Factor. For the national queue baseline, read US Interconnection Queue by the Numbers. For the backlog contrast in the country's largest queue, read PJM's Interconnection Queue Problem.

Share this

Load Factor tracks 38,000+ interconnection queue projects, withdrawn included, across 16 North American markets, with the evidence behind every developer it names.

Next step

See your market in 30 minutes.

A walkthrough of the projects, developers and evidence in the markets you work in.

Get the weekly brief

Queue movement, newly identified developers and the week’s deals, every Monday. Read past issues