The Load Factor Weekly · 2026-W44
Oct 26 – Nov 1, 2026
58 projects added (13.1 GW), 167 withdrawn, parent companies linked on 687
Published · by the Load Factor team
- 5813.1 GWProjects added
- 16730.4 GWWithdrawn
- 8407 MWMoved forward
- 1Developer identified
- 687Parent companies linked
In the week of Oct 26 – Nov 1, 2026, 58 projects (13.1 GW) first appeared in the queue data we track daily, 167 withdrew and 8 moved forward. Parent companies were linked on 687 projects, and a developer was identified on 1.
Queue movement
- Added
- MISO 49 (12.3 GW), ERCOT 9 (807 MW)
- Withdrawn
- MISO 161, PJM 4, SPP 1, ISO-NE 1
- Moved forward
- PJM 5 to in service, PJM 2 to agreement stage, PJM 1 to construction
- 1 project announced, not yet in a queue
Developers identified
1 project now names a developer (NYISO 1); parent companies were linked on 687 (West 181, MISO 141, CAISO 116, 249 elsewhere).
Examples- 0637NYISO solar, 100 MW
- WAPA-2023-G1West storage, 875 MW
- J1060MISO solar, 500 MW
Deals
5 deals · 2 financing, 2 M&A, 1 announcement- Arevon Closes on $120 Million Tax Equity Commitment with Wells Fargo for its Big Muddy Solar Project in…Tax equity, PR Newswire, Oct 27
- DOE announces $10.1B in loans to Constellation, Alliant, for 3.7 GWFinancing, Utility Dive, Oct 28
Load / data centers
No newly tracked data centers (tracked from Oct 29).
Sources: Queue movement: daily ISO queue releases through Nov 1 (MISO, PJM from Oct 17; CAISO, ERCOT, ISO-NE, NYISO, SPP from Oct 21); status and identification records applied Oct 26 – Nov 1, 2026; deals: deal records dated Oct 26 – Nov 1, 2026; data centers: Load Factor's site records (OpenStreetMap, Epoch AI, public records), changes tracked daily from Oct 29; nearby supply: the week's added queue projects within 25 mi. Renewable and unstated-fuel projects; PJM duplicates counted once.
Project IDs open in the Load Factor app.
Questions or tips for the brief? Write to [email protected].